- January 2025: Site preparation works.
- February 2025: Construction works commence, including demolition.
- June 2025: Project completion.
Kenmore Community Centre upgrade - Kenmore Hills
We're improving the Kenmore Community Centre for users.
Council is upgrading the Kenmore Community Centre. Kenmore Bridge Club, eWaste Connection and ShedWest Men's Shed currently use the centre. The works will improve access and usability.
Works include:
- demolition of the central building
- construction of a new building with a communal meeting space, rooms for the Bridge Club and Men's Shed and improved amenities
- other renovations to existing facilities for each community user group.
This project is jointly funded by the Australian Government and Brisbane City Council.
During construction, you may notice:
- construction noise
- increased dust
- low levels of vibration.
We'll provide advance notification of impactful works during construction.
We thank residents and users in advance for your patience and cooperation while we do these important works.
For more information, you can:
- phone the project team on 07 3178 5413 (8.30am-4.30pm, Monday to Friday)
- phone Council on 07 3403 8888 (after hours)
- email Council
- write to:
City Projects Office
Brisbane City Council
GPO Box 1434
Brisbane Qld 4001.