- Phase 1 (July-November 2011): Draft vision and concept plan released for public consultation.
- Phase 2 (November 2011 to early 2013): We released the Norman Creek 2012-2031 draft Master Plan for public comment in September 2012. We released the final master plan in early 2013.
- Phase 3 (2013-2031): Implementation commenced in early 2013.
- Completed works:
- 1st priority precinct, Coorparoo - Coorparoo Creek Park and Coorparoo Creek downstream works completed in 2017.
- 2nd priority precinct, Stones Corner - Hanlon Park / Bur'uda completed in 2022.
- 3rd priority precinct, Woolloongabba - Kingfisher Creek corridor concept plan project is underway.
- Glindemann Park, Holland Park upgraded in 2018.
- Completed works:
Norman Creek 2012-2031 Project
Council is improving the Normal Creek catchment to improve recreational opportunities for the community and improve environmental health.
Council's Norman Creek 2012 -2031 project aims to return the Noman Creek catchment to a more natural state. It also aims to revitalise the catchment to be an environmental and recreational asset.
The project covers an entire catchment of almost 30 square kilometres and is Australia's first whole of catchment urban water resources management project. It will create a 'big picture' guide for the future of the catchment.
The project goals focus on:
- improvements to the health of the waterways and ecosystems
- sport and recreation opportunities
- living with Brisbane’s climate - flood and drought
- strengthening community connections (physical and social) within the catchment.
Our vision is to create a catchment with:
- bikeways and footpaths connected to waterways
- accessible boardwalks and viewing platforms
- improved park and recreation spaces alongside creeks and healthy waterways
- shady sub-tropical habitats
- homes, buildings and neighbourhoods designed with water in mind and are resilient during times of drought and flood.
A master plan outlines the 20-year project.
View the Norman Creek catchment area map.
Norman Creek 2012-2031 Master Plan
The Norman Creek 2012-2031 Master Plan outlines key initiatives aimed at rejuvenating the Norman Creek catchment. It guides long-term investiment and community actions by outlining what's possible and where to focus our efforts in one of Brisbane's most urbanised catchments. The plan outlines the 20-year project designed to achieve multiple outcomes for the city. These include:
- strengthening Brisbane's economy
- improving access and inclusion for all residents
- making the city cleaner and greener.
Read more about Council's waterway projects, including Norman Creek.
For more information:
- phone Council on 07 3403 8888
- email Council
- write to:
Norman Creek 2012-2031 project team
Brisbane City Council
GPO Box 1434
Brisbane Qld 4001.