Monthly construction update - Main Street and Deakin Street connection

March 2024

Brisbane City Council is delivering the Main Street and Deakin Street connection as part of the Kangaroo Point Bridge to enhance safe walking and riding connections between Kangaroo Point and the CBD. Works to create the new Story Bridge underpass and new pathways on Main Street will continue in March 2024.

The Main Street and Deakin connection will improve walking and riding travel times and travel reliability by providing a direct route from Deakin Street and the eastern suburbs to the Kangaroo Point Bridge.

Construction

Construction activities for the Main Street and Deakin Street connection in March 2024 will include:

  • line marking the new pedestrian and bike path along Deakin Street to the new Story Bridge underpass
  • installing balustrading along the new Deakin Street ramp, bollards and signage in various locations on the site
  • constructing the new underpass flooring
  • installing pedestrian and bikeway lighting and electrical infrastructure on Main Street and in the Story Bridge underpass
  • ongoing construction of the new path connection from Main Street to the Story Bridge underpass.

What to expect

If you live in or are travelling through the area, you may notice:

  • localised traffic changes including reduced speed limits and short-term traffic disruptions including:
    • stop/go traffic control on Main Street and Deakin Street during construction hours
  • temporary path closures and detours with signage and traffic controllers onsite during works to direct pedestrians and cyclists around the work area
  • temporary work areas to safely undertake the works
  • construction noise, vibration and dust from machinery, including concrete saws and trucks
  • increased truck movements through the area to deliver machinery and materials.

Working hours

Construction will generally be undertaken from 7am to 6pm Monday to Friday and from 7am to 5pm on Saturdays.

Some out-of-hours works may be required to help minimise traffic disruptions and ensure the safety of pedestrians, motorists and workers. Advance notice will be provided for any planned out-of-hours works.

Register for updates

To receive construction updates via email register your details via the online form.

For more information about these works, contact Council’s project team by:

Date posted:
Last updated:

Brisbane City Council acknowledges this Country and its Traditional Custodians. We pay our respects to the Elders, those who have passed into the Dreaming; those here today; those of tomorrow.