What works are coming up?
We are pleased to advise construction of the new bridge is progressing well with the installation of deck units over the three bridge spans now complete.
Works on the bridge will continue with concrete pours and surface works to prepare for vehicles using the bridge early next year.
Around the site, works will also continue to relocate and replace services such as gas, water, drainage, sewer and electricity, rebuilding surrounding roads, property reinstatements and footpath construction.
When will this work take place?
Day works | Works will be carried out Monday to Saturday from 7am to 6am. |
---|---|
Night works | Works will be carried out Sunday to Thursday from 7.30pm to 5.30am. |
To ensure the safety of motorists and road workers and to minimise traffic and service disruptions, some work is required to be undertaken at night when traffic volumes are lowest.
Every effort will be made to complete particularly noisy works prior to 11pm, where possible
What does this work include?
The following works will be undertaken:
- construction of roads
- saw cutting of the road
- construction of service and drainage pits
- trenching and excavation to replace/install pipes
- relocation of existing underground services
- intermittent lane closures.
- Construction of concrete retaining walls.
How might this work impact me?
- Traffic control: reduced speed limits, lane closures, changes to traffic flow and short-term traffic disruptions.
- Noise, dust and vibration: noise and possible dust and vibration may be experienced from the construction activities.
- Temporary lighting: lighting towers are required to be used to light work areas at night to ensure worker safety.
- Access: impacted stakeholders will be contacted regarding any property access changes.
- Traffic delays: plan ahead and allow additional travel time.
Where will the works be?
Works will be carried out across the entire site at various times and dates.
Moggill Road service road (commercial):
- changed traffic conditions on the commercial service road are ongoing until April 2024.
- night works road closure/restricted access expected.
- on-street parking temporarily restricted.
Moggill Road service road (residential):
- night works and temporary road restricted access will continue.
- construction of new retaining walls and bridge works.
- public utility upgrades which include watermain, sewer main, electrical, telecommunications, gas and traffic signals are nearing completion.
- private property reinstatements are ongoing.
Moggill Road (between Payne Street and Waverley Road):
- lane closures (day and night)
- pedestrian footpath changes are expected.
- median concrete barrier and inbound lane pavement reconstruction are complete.
- public utility upgrades (water, sewer, gas and telecoms) are continuing.
Coonan Street:
- lane closures (day and night)
- service relocations and private property reinstatements continuing.
Belgrave Road and Coonan Street intersection:
- works were completed September 2023.
Local back streets (Nelson, Stanley, Payne, Vincent):
- trunk watermain works are complete.
- road resurfacing planned for completion late 2023
- sewer main, watermain, drainage, upgrades.
Keating Street near Coonan Street:
- exit onto Coonan Street closed early Jan 2024
- entrance from Coonan Street retained
- pavement and footpath reconstruction.
Stamford Road near Moggill Road
- left exit onto Moggill Road closed early 2024
- entrance from Moggill Road retained
- sewer main, watermain and drainage upgrades
- pavement and footpath reconstruction.
Temporary traffic changes
As works continue, new temporary traffic changes will be introduced across the project site.
- November – one inbound lane closure on Moggill Road day and night to allow for road reconstruction.
- November – one outbound lane on Moggill Road traffic will be switched to a new temporary alignment.
- January – Keating Street exit to Coonan Street will be closed.
If you are travelling through the works zone, please allow extra travel time, follow directional signage and traffic control.
Timing
Late 2021 | Start of major civil construction |
Now | Bridge foundation installed |
Late 2024 | Project completion. |
Contact us
To find out more about these works or the project, you can contact us via:
- phone: 1800 572 132 (business hours) or 3403 8888 (24-hours)
- email.