Burwood Road bridge embankment repairs

Works to repair and improve the embankment under the Burwood Road bridge in Mitchelton are now complete.

Project summary

This table includes project summary information on the Burwood Road bridge embankment repairs
AddressBurwood Road, Mitchelton
WardsEnoggera and McDowall
Project outcomesRepair erosion and ensure the resilience of the bridge
Latest newsWorks are complete

About the project 

The embankment under the Burwood Road bridge, along the Kedron Brook experienced severe erosion and damage from flood waters.

In mid-2022 we undertook temporary erosion protection works on the bridge abutment and piers, as part of the Kedron Brook restoration program. Works included placing large rocks in sections where erosion had occurred to ensure the resilience of the bridge and nearby abutments while we investigated a permanent solution.

Our permanent solution involved stabilising the embankment around the bridge foundations by installing rock protection around the base of the bridge piles, batter and abutment.

These permanent improvement works are now complete and will ensure the resilience of the bridge during future severe weather and reduce the need for ongoing maintenance works.

Project timing

Construction started in late February 2024 and was completed in mid-May 2024. 

More information

If you would like to find out more about this project, you can:

  • phone the project team on 1800 884 681 during business hours
  • phone Council on 07 3403 8888 outside of business hours
  • email the project team

For more information about our restoration works following the 2022 severe weather event, visit our Kedron Brook restoration works page.

Last updated:

Brisbane City Council acknowledges this Country and its Traditional Custodians. We pay our respects to the Elders, those who have passed into the dreaming; those here today; those of tomorrow.