North Brisbane Bikeway: Stage 5 - Dickson Street to Kedron Brook Bikeway – Wooloowin

Brisbane City Council is now planning a potential connection between the North Brisbane Bikeway on Dickson Street and Kedron Brook Bikeway at Brook Road, via Kent Road.

About the project

The North Brisbane Bikeway is an important active transport corridor in Brisbane’s north, which we are delivering in partnership with the Queensland Government. It connects the CBD with Brisbane’s northern suburbs and will connect with the Kedron Brook Bikeway to expand our active transport network.

This project will complete the final link between the Queensland Government’s North Brisbane Bikeway on Dickson Street and the Kedron Brook Bikeway. 

Community engagement

Council has engaged with the community about this connection over several years. 

In 2021, we released a concept design that connected to the Kedron Brook via Dickson and Jackson streets (Price Street to Kedron Brook). Through the engagement process, there were some elements of the design the community asked Council to consider further. 

In early 2024, we established a Community Working Group to consider the design and provide input on the Price Street to Kedron Brook alignment. The valuable insights gathered from this group have been reviewed along with technical input and feasibility.  

Project alignment

Since the conclusion of the Community Working Group, the local councillor, Cr Julia Dixon, has raised broader concerns from the community about the Price Street to Kedron Brook alignment. Additionally Council has received two petitions regarding NBB Stage 5. One indicated there is still broad community support to complete Stage 5 and another requesting Council consider the Kent Road alignment. Council’s Establishment and Coordination Committee endorsed responses to these petitions on 20 January 2025. 

The Kent Road concept design was released in 2018 and proposed travelling east-west to Kent Road via Price Street then across Rose Street into Park Road, finally connecting to the Kedron Brook Bikeway at Brook Road. 

In recognition of the concerns raised by the community, Cr Dixon has indicated support for the Kent Road as the preferred alignment. 

Given the important role this bikeway connection would serve in the active transport network, and recognising the community interest, Council will discontinue work on the Price Street to Kedron Brook alignment and resume work on the previous Kent Road alignment.

What’s next? 

Council will seek funding from the Queensland Government to progress the preferred Kent Road alignment. 

We will provide an update to the community about this project should more information become available in the future. 

More information

If you would like to find out more about the North Brisbane Bikeway: Stage 5 project, you can:

  • phone the project team on 07 3178 5413 during business hours
  • phone Council on 07 3403 8888 outside of business hours
  • email the project team.