March 2024
Construction activities in March will include:
- continued works in the CBD site compound including earthworks and concreting for the plaza area
- relocating the navigation channel closer to the CBD and underneath the bridge structure to allow marine works to progress towards Kangaroo Point which involves:
- reducing the vessel clearance height to 12.3m above sea level
- installation of final overwater bridge deck span over the navigation channel
- continued construction of the above-water restaurant and bar and the café in the CBD plaza area
- continued closure of the City Botanic Gardens Riverwalk for approximately four months.
What to expect
Expected impacts:
- construction activities including excavation, steel fixing, welding, scaffolding and concreting works
- barge movements for materials and equipment deliveries
- noise and low levels of vibration associated with the use of equipment and machinery such as cranes, drill rigs, concrete pumps and trucks
- lighting associated with night works
- deliveries of machinery and equipment to the CBD site.
- traffic control and signage to direct pedestrians, cyclists, scooter riders and motorists around work areas.
Construction map
The map below shows the indicative construction sites and progress of the bridge structure. Please note the riverside shared pathway in C.T. White Park has been reinstated and the temporary shared path has been removed.
Accessible version
Construction hours
Works will generally be undertaken from 6.30am to 6.30pm, Monday to Friday and 6.30am to 5pm on Saturdays.
Out-of-hours works are required due to lane closure requirements, ambient temperatures, tide levels and size of concrete pours.
Upcoming out-of-hours works will include:
- intermittent concrete pours from the CBD site from 3am, Monday to Saturday
- intermittent overnight concrete pours from the CBD site to the marine construction area between 6.30pm and 6.30am, Monday to Saturday
- some night deliveries to the CBD worksite which may be required between 6.30pm and 6.30am, Monday to Saturday to minimise impacts to road users
- low-impact bridge deck construction activities will continue until 4am, Monday to Saturday and includes steel fixing, welding, transporting equipment and materials on barges and crane lifts
- intermittent low-impact bridge works in the marine area will also continue, including the removal of temporary marine structures and cable stay installation and stressing from 5am-11pm, Monday to Saturday, weather and conditions permitting.
Contact Connect Brisbane
For more information about these works, contact Connect Brisbane by:
- calling 1800 864 221 (during business hours), or
- emailing the project team.