March 2024
Construction activities in March will include:
- continued works in Scott Street including earthworks and concreting for the construction of the northern footpath
- continued installation of concrete furniture and garden beds on the bridge deck
- commence installation of precast stairs connecting Scott Street to C.T. White Park
- commence installation the pedestrian shade canopy and privacy screens on the bridge deck
- opening the riverside shared pathway in C.T. White Park and removing the temporary shared path
- bridge deck concrete pours from the marine construction area
- relocating the navigation channel closer to the CBD and underneath the bridge structure to allow marine works to progress towards Kangaroo Point which involves:
- reducing the vessel clearance height to 12.3m above sea level
- installation of final overwater bridge deck span over the navigation channel.
What to expect
Expected impacts:
- construction activities including excavation, steel fixing, welding, scaffolding and concreting works
- barge movements for materials and equipment deliveries
- noise and low levels of vibration associated with the use of equipment and machinery such as cranes, rock breakers, concrete pumps, excavators and trucks
- lighting associated with night works
- traffic control and signage to direct pedestrians, cyclists, scooter riders and motorists around work as required.
Construction map
The map below shows the indicative construction sites and progress of the bridge structure. Please note the riverside shared pathway in C.T. White Park has been reinstated and the temporary shared path has been removed.
Accessible version
Construction hours
Where possible, works will be undertaken during standard hours from 6.30am to 6.30pm, Monday to Friday and 6.30am to 5pm on Saturdays.
Out-of-hours works are required due to lane closure requirements, ambient temperatures, tide levels and size of concrete pours.
Upcoming out-of-hours works will include:
- intermittent concrete pours from the Kangaroo Point site from 5am, Monday to Saturday
- intermittent overnight concrete pours from the CBD site to the marine construction area between 6.30pm and 6.30am, Monday to Saturday
- low-impact bridge deck construction activities will continue until 4am, Monday to Saturday and includes steel fixing, welding, transporting equipment and materials on barges and crane lifts
- intermittent low-impact bridge works in the marine area will also continue, including the removal of temporary marine structures and stay cable installation and stressing from 5am-11pm, Monday to Saturday, weather and conditions permitting.